Great Britain
G98 or G99 for solar and batteries?
It depends on how much generation sits on each phase of the supply, counting every inverter at that connection, batteries included.
- G98
- Fully type tested equipment, 16 A per phase or less in total: 3.68 kW on single phase, 11.04 kW on three phase (at 230 V). Connect, then notify the network operator: no later than 28 days after commissioning, counting the day of commissioning.
- G99
- Anything above that. In most cases you apply and wait for the operator's answer before installing, with the fast routes below as exceptions.
A 3 kW solar inverter plus a 3 kW battery inverter on one phase is more than 16 A, so it is G99. A programme of several premises close together needs an application first even when each one is small.
G99 fast routes for small installations
All of them need fully type tested inverters, a single installation and units of 32 A per phase at most.
| Route | Size, per phase | Export limited to | How it goes |
|---|---|---|---|
| SGI-1 | Each unit and the total up to 16 A (a larger unit limited to 16 A) | No separate limit | Install and commission, then notify (Form A3-3) |
| SGI-2 | Each unit up to 16 A, total under 32 A | 16 A | Apply (Form A1-2) and wait; a result within 10 working days |
| SGI-3 | Each unit up to 32 A, total under 60 A | 32 A (waived if the total is 32 A or less) | Apply (Form A1-2); within 10 working days the operator says if a study is needed |
For SGI-2 and SGI-3 the planned commissioning date is between 10 working days and 3 months after applying, and commissioning is confirmed within 28 days (Form A3-2). An export limiting scheme has its own requirements under G100. Outside these routes, nothing is installed before the operator answers.
Other dates to keep in mind
- MCS certificate, current scheme
- No later than 10 working days after commissioning. The current scheme closes on 31 March 2027.
- MCS certificate, MCS:2025
- No later than 30 calendar days after commissioning.
- G99, installation document
- Within 28 days of commissioning where the operator does not witness it.
- G99, standard application
- The operator has up to 45 working days to quote for low voltage works (65 for higher voltages), counted from complete information and any fee.
Rules last checked on 29 November 2026. This is a summary, not design or legal advice: the documents and your network operator decide. Sources: ENA G98 Issue 2, ENA G99 Issue 2, MIS 3002 6.0, MCS installer operating requirements, MCS transition, guaranteed standards.